Photo Gallery
Overview
Systems
- Titan I
- Titan II
- Titan IIIA
- Starbird
- Aries
- Super Loki
Other Programs
Cost: $4,758,595
Launch Complex 20 Highlights
- 23 April 1956 – Contract awarded
- February 1957 – Construction underway
- 10 September 1959 – Construction completed
- 10 September 1959 – Air Force accepted the launch complex
- 1 July 1960 – First Titan I launch
- 13 December 1961 – Last Titan I launch
- 21 November 1961 – First “blue suit” (U.S. Air Force crew) Titan I launch from this pad
- Total Titan I launched – 16
- 1962 – Pad transferred for space missions
- September 1963 – Modified to accommodate a third stage
- 1 September 1964 – First Titan IIIA launch
- 6 May 1965 – Last Titan IIIA launch
- Total Titan IIIA launched – 4
- Following the last Titan IIIA launch, the launch complex was deactivated
- The complex was programmed to support the Air Force X-20 DYNA SOAR effort, but program was cancelled
- April 1967 – Complex deactivated
- 13 June 1967 – Sold for salvage
- 1 November 1988 – Began modification by Butler Construction Co. under a SDIO contract for 2 Starbird program Pads 20A and 20B
- December 1989 – Modification work completed and turned over to the Range. The facility consisted of two launch pads with 58′ rail launchers, two launch equipment buildings, a launch support center and a payload assembly building
- 18 December 1990 – First 4-stage Starbird launched from Pad 20A
- 18 June 1991 – University-sponsored sub-orbital Joust-1 launched with Castor solid motor; failed
- 20 August 1991 and 14 October 1991 – Strategic Defense Initiative Organization’s two-stage Aries solid rocket, Red Tigress 1A and 1B, launched
- 23 May 1991 and 28 May 1993 – Two Red Tigress II series, 2A and 2B, launched using the Starbird booster
- 1995 – Electronic equipment and launchers removed
- 21 January, 12 December and 13 December 2000 – Three Super Loki launched